Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.25 | 6.25 | 0.000 | 6.25 | 6.250 | 0.000 |
30W1461 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ENC Letter No. 895/07Yata-PMGSY-Ni. III
TS Amount (lakhs) : 66.03 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
66.03
Resanction Cost :
66.03
Tentative Cost :
66.03
Exp. Upto Last Fy : 24.61
For CFY 2024-2025
Remaining : 41.42
Demand : 41.42
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 24.61
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पैच का कार्य पूर्ण। सेतु पर रंग-रोगन का कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 07-Nov-2023
Physical Peramenters