Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 41 | 41 | 0.000 | 41 | 41.000 | 0.000 |
30W1521 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 212/III(2)/2024-01(Pra.Aa)/2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
148.22
Resanction Cost :
148.22
Tentative Cost :
148.22
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 148.22
Demand : 110.93
Allotment : 48.00
Exp in CFY : 48.01
Total Up to Date Exp : 48.01
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 60 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
1 month 1 week from now
30 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 03-Jul-2024
Physical Peramenters