Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
39W531 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी का पत्र संख्या 786/अर्थ एवं संख्या (fनयोजन fवभाग) /2015-16 fदनांक 23.12.2015
TS Amount (lakhs) : 48.95 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
48.95
Resanction Cost :
48.95
Tentative Cost :
48.95
Exp. Upto Last Fy : 43.55
For CFY 2024-2025
Remaining : 5.40
Demand : 5.41
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 43.55
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
8 years 6 months ago
23 Dec 2015
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 30-Mar-2023
Physical Peramenters