Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
39W832 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 498(1)/।।।(2)/22-08(एमएलए)/2017 टीसी दिनांक 07.01.2022
TS Amount (lakhs) : 97.5 Lacs
Financial Detail
Sanction Cost : 97.51 Lacs
Resanction Cost : 97.51 Lacs
Exp. Upto Last Fy : 90.85 Lacs
For CFY 2024-2025
Remaining : 6.66 Lacs
Demand : 6.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 90.85 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
2 years 4 months ago
07 Jan 2022
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.00 किमी0 में पहाड कटान कार्य पूर्ण। दायित्व शेष। -- as on 30-Jun-2023
Physical Peramenters