Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2.000 | 0 | 0.000 | 0.000 |
39W929 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. ।/111862/2023 ई-फाईल सं0 51812 /लोक निर्माण अनुभाग-2 दिनांक 31.03.2023
TS Amount (lakhs) : 117.16 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
117.16
Resanction Cost :
117.16
Tentative Cost :
117.16
Exp. Upto Last Fy : 83.50
For CFY 2024-2025
Remaining : 33.66
Demand : 30.00
Allotment : 25.80
Exp in CFY : 25.79
Total Up to Date Exp : 109.29
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
4 months 5 days ago
12 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.0 किमी0 में दीवार निर्माण कार्य पूर्ण। -- as on 31-Mar-2024
Physical Peramenters