Work Profile Report [39W929]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. ।/111862/2023 ई-फाईल सं0 51812 /लोक निर्माण अनुभाग-2 दिनांक 31.03.2023
TS Amount (lakhs) : 117.16 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
117.16
Resanction Cost :
117.16
Tentative Cost :
117.16
Exp. Upto Last Fy :
83.50
For CFY 2024-2025
Remaining :
33.66
Demand :
30.00
Allotment :
25.80
Exp in CFY :
25.79
Total Up to Date Exp :
109.29
Work completed
Sanction on : 1 year 8 months ago
31 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 9 months 1 week ago
12 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2.0 किमी0 में दीवार निर्माण कार्य पूर्ण। -- as on 31-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: