Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15.75 | 15.75 | 0.000 | 15.75 | 5.750 | 0.000 |
3W654 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 895/07Yata-PMGSY-Ni III dated 16-05-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 271.73 Lacs
Resanction Cost : 271.73 Lacs
Exp. Upto Last Fy : 159.14 Lacs
For CFY 2024-2025
Remaining : 112.59 Lacs
Demand : 112.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 159.14 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
13.00 किमी0 पी0सी0 का कार्य पूर्ण। दीवारों एवं काॅजवें, कच्ची नाली का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 24-Apr-2024
Physical Peramenters