Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.7 | 1.7 | 0.000 | 1.7 | 0.000 | 0.000 |
40W492 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा॰सं॰ 28022-0465/2023 दिनंाक 28.03.202
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 79.29 Lacs
Resanction Cost : 79.29 Lacs
Exp. Upto Last Fy : 43.01 Lacs
For CFY 2024-2025
Remaining : 36.28 Lacs
Demand : 30.00 Lacs
Allotment : 15.00 Lacs
Exp in CFY : 2.52 Lacs
Total Up to Date Exp : 45.53 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
1 year 1 month ago
28 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान कार्य प्रगति पर। -- as on 22-Mar-2024
Physical Peramenters