Work Profile Report [40W542]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई-फाईल संख्या 50637/140131/2023 दिनंाक 24-7-2023
TS Amount (lakhs) : 470.35 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
470.35
Resanction Cost :
470.35
Tentative Cost :
470.35
Exp. Upto Last Fy :
124.04
For CFY 2024-2025
Remaining :
346.31
Demand :
278.73
Allotment :
162.75
Exp in CFY :
162.75
Total Up to Date Exp :
286.79
Construction Started
Sanction on : 1 year 5 months ago
24 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
5 %
Up to Date :
70 %
Tentative Completion date on : 3 months 2 weeks from now
13 Apr 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान, स्कपर निर्माण, दीवार निर्माण , एवं जी0-1 व जी0-2 का कार्य पूर्ण । जी0-3 व पी0सी0 का कार्य प्रगति पर। -- as on 04-Nov-2024
Assets :
Road ID on IM : Road 1
Bridges on The Basis of AI:
© PWD Uttarakhand