Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 0.000 | 6 | 0.000 | 0.000 |
40W542 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाईल संख्या 50637/140131/2023 दिनंाक 24-7-2023
TS Amount (lakhs) : 470.35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
470.35
Resanction Cost :
470.35
Tentative Cost :
470.35
Exp. Upto Last Fy : 124.04
For CFY 2024-2025
Remaining : 346.31
Demand : 200.00
Allotment : 46.00
Exp in CFY : 45.22
Total Up to Date Exp : 169.26
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 45 %
Sanction on :
11 months 3 weeks ago
24 Jul 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान, स्कैपर निर्माण, दीवार निर्माण , Wbm G1 का कार्य पूर्ण एवं Wbm G2 का कार्य प्रगति पर। -- as on 02-Jul-2024