Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 3.6 | 3.6 | 0 |
43W464 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 4531/111(2)/15-13(प्रा0आ0)/2015 दि0 05.06.2015
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
50.85
Resanction Cost :
50.85
Tentative Cost :
50.85
Exp. Upto Last Fy : 28.42
For CFY 2024-2025
Remaining : 22.43
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 28.42
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
9 years 1 month ago
05 Jun 2015
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रतिकर वितरण कार्य प्रगति पर है । -- as on 16-May-2024
Physical Peramenters