Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.2 | 2.2 | 1.900 | 0.3 | 0.300 | 0.000 |
43W579 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 स0 2207/111(2)/16-12(एमएलए)/2016 दि0 26.07.2016
TS Amount (lakhs) : 140.59 Lacs
Financial Detail
Sanction Cost : 140.59 Lacs
Resanction Cost : 147.96 Lacs
Exp. Upto Last Fy : 121.58 Lacs
For CFY 2024-2025
Remaining : 26.38 Lacs
Demand : 19.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 121.58 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 78 %
Up to Date : 78 %
Sanction on :
7 years 9 months ago
26 Jul 2016
Tentative Completion date:
7 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान कार्य पूर्ण ।किमी0 2 में पार्ट 2 कार्य प्रगति पर । दि0 31.12.2024 तक कार्य पूर्ण कर लिया जायेगा। -- as on 02-May-2024
Physical Peramenters