Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.9 | 3.9 | 2.900 | 1 | 1.000 | 0.100 |
43W585 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 2388/111(2)16-9(एमएलए)/ 2015 दि0 01.09.2016
TS Amount (lakhs) : 261.2 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
261.20
Resanction Cost :
261.20
Tentative Cost :
261.20
Exp. Upto Last Fy : 227.05
For CFY 2024-2025
Remaining : 34.15
Demand : 34.15
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 227.05
Construction Started
Physical Progress:
At start of FY 2024-2025 : 74 %
Up to Date : 74 %
Sanction on :
7 years 10 months ago
01 Sep 2016
Tentative Completion date:
8 months 1 week from now
27 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 09-May-2024