Work Profile Report [44W622]
Tenders
Project Activities
alerts
Administrative Approval Detail : शासनादेश संख्या-4990(1)/।।।(2)/21-39 (प्रा0आ0)/2018 दिनंाक 22 अक्टूबर, 2021
TS Amount (lakhs) : 6287.93 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
6886.20
Resanction Cost :
6886.20
Tentative Cost :
6886.20
Exp. Upto Last Fy :
5,886.07
For CFY 2025-2026
Remaining :
1,000.13
Demand :
1,000.13
Allotment :
530.13
Exp in CFY :
170.65
Total Up to Date Exp :
6,056.72
Construction Started
Sanction on : 3 years 8 months ago
22 Oct 2021
Physical Progress:
At start of FY 2025-2026 :
72 %
Up to Date :
85 %
Tentative Completion date on : 3 days 9 hours ago
15 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दिनांक 15.07.2025 तक सेतु के पहुंच मार्ग का कार्य कराया जना प्रस्तावित है। -- as on 03-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: Laxman jhula Pedestrain Bridge
© PWD Uttarakhand