Work Profile

45W182 :

No Pic Avilable Time series Gantt
घनसाली-मूलगढ-चिरबिटिया मोटर मार्ग के कि0मी0-17 थौलधार, सरोली-धारगांव-मयाली तक मोटर मार्ग का नव निर्माण कार्य।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शा0सं0 1542/।।।(2)/20-09(एम0एल0ए0)/2017टी0सी0,दि0-04.09.2020

TS Amount (lakhs) : 0 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

14.19

Resanction Cost :

14.19

Tentative Cost :

14.19

Exp. Upto Last Fy : 1.22

For CFY 2024-2025

Remaining : 12.97

Demand : 1.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 1.22

Survey work done

Physical Progress:

At start of FY 2024-2025 : 0 %

Up to Date : 0 %

Sanction on :
3 years 10 months ago
04 Sep 2020


Tentative Completion date:
2 years 3 months ago
31 Mar 2022


Actual Completion Date:
Not Yet Reported


Rating : 9

Remark

Bottelneck: Alignment Dispute


सर्वेक्षण पूर्ण। -- as on 08-Sep-2023

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 4 4 0.000 4 0.000 0.000
Currently only Bank Gaurantee information is avilable