Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11 | 5.5 | 0.000 | 5.5 | 0.000 | 0.000 |
47W25 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 5108(।)/111-(2)/11-23 (प्रा0 आ0)/ 2009 दि0 26.09.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
138.60
Resanction Cost :
138.60
Tentative Cost :
138.60
Exp. Upto Last Fy : 40.19
For CFY 2024-2025
Remaining : 98.41
Demand : 10.00
Allotment : 0.25
Exp in CFY : 0.25
Total Up to Date Exp : 40.44
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
12 years 9 months ago
26 Sep 2011
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 17: AIP Govt of India
Bottelneck: no issue
अपर पमुख वन संरक्षक एवं नोड़ल अधिकारी देहरादून द्वारा आॅन लाईन कम्प्लाईन्स दिनांक 24.02.2023 को सत्यापित की जा चुकी है। -- as on 14-Jul-2024
Physical Peramenters