Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6 | 0 |
47W356 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 5221/।।।(2)/18-10(एम0एल0ए0)/2017 टी0सी0 दिनांक 23.10.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 30.00 Lacs
Resanction Cost : 30.00 Lacs
Exp. Upto Last Fy : 8.82 Lacs
For CFY 2024-2025
Remaining : 21.18 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 8.82 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 years 6 months ago
23 Oct 2018
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
म्यूटेशन नोड़ल अधिकारी द्वारा सत्यापित की जा चुकी है। -- as on 23-Dec-2023
Physical Peramenters