Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 14.3 | 14.3 | 7.000 | 7.3 | 7.300 | 4.300 |
53W1551 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1173/।।।(3)/2021-40(सी.आार.आई.एफ.)/2021 दिनांक 27.10.2021
TS Amount (lakhs) : 7753 Lacs
Financial Detail
Sanction Cost : 7,753.00 Lacs
Resanction Cost : 7,753.00 Lacs
Exp. Upto Last Fy : 5,844.06 Lacs
For CFY 2024-2025
Remaining : 1,908.94 Lacs
Demand : 1,908.93 Lacs
Allotment : 500.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 5,844.06 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 88 %
Sanction on :
2 years 6 months ago
27 Oct 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
माननीय उच्च न्यायालय में जनहित याचिका सं0 68/2022 पर दिनांक 04.08.2022 को सुनवाई के दौरान मार्ग पर वृक्षों के पातन एवं ट्रान्सप्लान्ट पर रोक लगाई गई थी। वर्तमान में रोक हटा दी गई है जिसके अनुपालन में 1006 यूकेलिप्टिस के वृक्षों के सापेक्ष 1006 वृक्षों का पातन एवं 1006 जडें हटाने का कार्य तथा 972 वृक्षों के सापेक्ष 970 वृक्षो का ट्रान्सप्लान्ट किया जा चुका है। 737 विद्युत पोलों के सापेक्ष 725 पोल शिफ्ट किये जा चुके है। 13.800 किमी0 विद्युत लाईन शिफ्ट, 24.82 किमी0 लम्बाई में यू0डेªन तथा 1.20 किमी0 लम्बाई में वैकिलर डेªन, 24.00 किमी0 लम्बाई में के0सी0 डेªन एवं मिडियन का कार्य पूर्ण। -- as on 15-May-2024
Physical Peramenters