Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.325 | 1.325 | 0.600 | 0.725 | 0.720 | 0.000 |
53W1651 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 54048 दिनांक 14.07.2023
TS Amount (lakhs) : 76.32 Lacs
Financial Detail
Sanction Cost : 76.32 Lacs
Resanction Cost : 76.32 Lacs
Exp. Upto Last Fy : 35.95 Lacs
For CFY 2024-2025
Remaining : 40.37 Lacs
Demand : 40.00 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 21.28 Lacs
Total Up to Date Exp : 57.24 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 45 %
Sanction on :
10 months 5 days ago
14 Jul 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 07-Jan-2024