Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.3 | 1.3 | 0.000 | 1.3 | 0.000 | 0.000 |
53W1702 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : नागरिक उड्डयन विकास प्राधिकरण की ई0 पत्रावली सं0 37808, पत्रावली सं0 186717/24 190(9)/2007 टी0सी0 दिनांक 02.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
148.33
Resanction Cost :
148.33
Tentative Cost :
148.33
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 148.33
Demand : 148.33
Allotment : 59.33
Exp in CFY : 54.79
Total Up to Date Exp : 54.79
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 80 %
Sanction on :
6 months 2 weeks ago
02 Jan 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डी0बी0एम0 का कार्य प्रगति पर है। -- as on 29-Jun-2024
Physical Peramenters