Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 17.4 | 13.4 | 13.4 | 0 |
Closed Work 55W1368 :
Administrative Approval Detail : शासनादेश संख्या 112/।।।(3)/2020-31 (सी0आर0एफ0)/2019 दि0 17.02.2020
TS Amount (lakhs) : 878.39 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
878.39
Resanction Cost :
878.39
Tentative Cost :
878.39
Exp. Upto Last Fy : 874.00
For CFY 2024-2025
Remaining : 4.39
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 874.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
4 years 5 months ago
17 Feb 2020
Tentative Completion date:
3 years 1 month ago
15 Jun 2021
Actual Completion Date:
2 years 1 month ago
30 May 2022
Remark
Bottelneck: no issue
कार्यपूर्ण दायित्वों का भुगतान शेष। -- as on 16-Jun-2022