Work Profile Report [55W1952]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/239937/2024/PWD2-BUD/ANBU/36/2023-III-2-Public Works Department
TS Amount (lakhs) : 63.6 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
63.60
Resanction Cost :
63.60
Tentative Cost :
63.60
Exp. Upto Last Fy :
48.55
For CFY 2025-2026
Remaining :
15.05
Demand :
6.29
Allotment :
4.32
Exp in CFY :
4.32
Total Up to Date Exp :
52.87
Work completed
Sanction on : 1 year 4 months ago
13 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
97 %
Tentative Completion date on : 3 months 6 days from now
30 Apr 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रथम चरण के अन्तर्गत भूमि प्रतिकर का एक काश्तकार को छोड़कर कार्य पूर्ण। गाईड बंध की स्वीकृति प्राप्त। कार्य प्रगति में है। -- as on 30-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: