Work Profile Report [55W1978]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/261888/2024/PWD2-BUD/ANBU/28/2023-III-2-Public Works Department-Part(1)
TS Amount (lakhs) : 87.76 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
87.76
Resanction Cost :
87.76
Tentative Cost :
87.76
Exp. Upto Last Fy :
0.11
For CFY 2025-2026
Remaining :
87.65
Demand :
60.00
Allotment :
50.01
Exp in CFY :
50.01
Total Up to Date Exp :
50.13
Construction Started
Sanction on : 7 months 3 weeks ago
17 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
80 %
Tentative Completion date on : 4 months 3 weeks from now
31 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
1.50 कि0मी0 में कार्यपूर्ण, शेष कार्य प्रगति में है। -- as on 30-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: