Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.42 | 2.12 | 2.120 | 0 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 1 | 0 | 0 | 0 |
Span of Bridges [m] | 300 | 300 | 300.000 | 0 | 0.000 | 0.000 |
59W1828 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 49/।।।(3)/2021-27(सी.आर.एफ.)2019 दि0 11.01.2021
TS Amount (lakhs) : 2357.46 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
2602.24
Resanction Cost :
2602.24
Tentative Cost :
2602.24
Exp. Upto Last Fy : 2,292.67
For CFY 2024-2025
Remaining : 309.57
Demand : 64.79
Allotment : 64.79
Exp in CFY : 64.50
Total Up to Date Exp : 2,357.17
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 6 months ago
11 Jan 2021
Tentative Completion date:
2 years 5 months ago
31 Jan 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
Work completed 03/2024 -- as on 02-Apr-2024
Physical Peramenters