Work Profile Report [5W35]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 3138/101-2/06-61 (प्रा0आ0)/06दिनांक 22.11.2006
TS Amount (lakhs) : 142 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
142.00
Resanction Cost :
142.00
Tentative Cost :
142.00
Exp. Upto Last Fy :
105.50
For CFY 2024-2025
Remaining :
36.50
Demand :
12.10
Allotment :
10.00
Exp in CFY :
7.10
Total Up to Date Exp :
112.60
Construction Started
Sanction on : 18 years 1 month ago
22 Nov 2006
Physical Progress:
At start of FY 2024-2025 :
45 %
Up to Date :
55 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
1.60 किमी0 पहाड़ कटान कार्य पूर्ण। 1.60 किमी0 पार्ट-।। कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 02-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: