Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 1.600 | 6.4 | 0.000 | 0.000 |
5W35 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 3138/101-2/06-61 (प्रा0आ0)/06दिनांक 22.11.2006
TS Amount (lakhs) : 142 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
142.00
Resanction Cost :
142.00
Tentative Cost :
142.00
Exp. Upto Last Fy : 105.50
For CFY 2024-2025
Remaining : 36.50
Demand : 20.00
Allotment : 10.00
Exp in CFY : 7.10
Total Up to Date Exp : 112.60
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 45 %
Sanction on :
17 years 7 months ago
22 Nov 2006
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
1.60 किमी0 पहाड़ कटान कार्य पूर्ण। 1.60 किमी0 पार्ट-।। कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 02-Apr-2024
Physical Peramenters