Work Profile Report [61W11]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : भारत सरकार के पत्र संख्या RO/UK/12014/89/Annual Plan/2019-20, Dt. 12-02-2020जाॅब संख्या NH-121 (309)-UR-2019-20-555
TS Amount (lakhs) : 829.23 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
829.23
Resanction Cost :
829.23
Tentative Cost :
829.23
Exp. Upto Last Fy :
33.17
For CFY 2024-2025
Remaining :
796.06
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
33.17
Construction Started
Sanction on : 4 years 11 months ago
12 Feb 2020
Physical Progress:
At start of FY 2024-2025 :
14 %
Up to Date :
14 %
Tentative Completion date on : 2 years 7 months ago
21 Jun 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Diversion work completed. Well foundation work stopped by JIM Corbett Authority from feb 2021 to 12-06-2021. After approval of CWLW, A1 and A2 well foundation work in progress.. -- as on 17-Aug-2021
Assets :
© PWD Uttarakhand