Work Profile Report [62W1]
Fin Plan
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : RO/UK/12014/92/Annual plan/2019-20 dated 12.02.2020 ( job. no NH-123(507)-UR-2019-20-556)
TS Amount (lakhs) : 2314.03 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2314.03
Resanction Cost :
2314.03
Tentative Cost :
2314.03
Exp. Upto Last Fy :
1,458.98
For CFY 2024-2025
Remaining :
855.05
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1,458.98
Construction Started
Sanction on : 4 years 10 months ago
12 Feb 2020
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 2 years 10 months ago
20 Feb 2022
Actual Completion Date : 3 years 1 month ago
15 Nov 2021
Physical Linear Components
Remark
physical progress-100.00%
DBM completed-19.00 km
BC completed- 19.00 km
-- as on 14-Jun-2022
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2 Road 3
Bridges on The Basis of AI: Yamuna Bridge Badri bridge local nala