Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 19 | 19 | 19 | 0 |
Closed Work 62W1 :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: Yamuna Bridge Badri bridge local nala
Administrative Approval Detail : RO/UK/12014/92/Annual plan/2019-20 dated 12.02.2020 ( job. no NH-123(507)-UR-2019-20-556)
TS Amount (lakhs) : 2314.03 Lacs
Financial Detail
Sanction Cost : 2,314.03 Lacs
Resanction Cost : 2,314.03 Lacs
Exp. Upto Last Fy : 1,458.98 Lacs
For CFY 2024-2025
Remaining : 855.05 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1,458.98 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
4 years 4 months ago
12 Feb 2020
Tentative Completion date:
2 years 4 months ago
20 Feb 2022
Actual Completion Date:
2 years 7 months ago
15 Nov 2021
Remark
Bottelneck: no issue
physical progress-100.00%
DBM completed-19.00 km
BC completed- 19.00 km
-- as on 14-Jun-2022
Physical Peramenters