Work Profile Report [62W5]

Rehabilitation and ugradation to 2-lane with paved shoulder configuration from existing km 122.00(Dharasu bend) to km 147.230 (Silkyara bend)(desigh Ch. 0.00 to 24.30)of NH-94 in the state of Uttarakhand on EPC mode under improvement to NH connectivity to Chardham.
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

  • alerts
  • Documents

    Samples

Administrative Approval Detail : एन0एच0 12014/105/2016/यू0आर0/चारधाम/एन0एच0-2job no. NH-94-UR-2016-17-496

TS Amount (lakhs) : 23780.53 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

23780.00

Resanction Cost :

23780.00

Tentative Cost :

23780.00

Exp. Upto Last Fy :

15,207.72

For CFY 2024-2025

Remaining :

8,572.28

Demand :

1,000.00

Allotment :

256.28

Exp in CFY :

256.28

Total Up to Date Exp :

15,464.00

Construction Started

Sanction on : 7 years 7 months ago

28 Mar 2017

Physical Progress:

At start of FY 2024-2025 :

96 %

Up to Date :

97 %

Tentative Completion date on : 6 months 3 weeks ago

30 Apr 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
24.3
24.3
22.180
2.12
0.800
0.500
Bridge
2 (28m)
2 (28m)
0 (0.000m)
2 (28m)
0 (0.000m)
0 (0.000m)

Remark

view all

physical progress 97.42 %
financial progress-95.20 %
-- as on 06-Jun-2024

Rating : 97

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1 Road 2 Road 3

Bridges on The Basis of AI: Margaon Bridge Junga Bridge local nala

© PWD Uttarakhand