Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 24.3 | 24.3 | 22.180 | 2.12 | 0.800 | 0.500 |
No of Bridges | 2 | 2 | 0 | 2 | 0 | 0 |
Span of Bridges [m] | 28 | 28 | 0.000 | 28 | 0.000 | 0.000 |
62W5 :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2 Road 3
Bridges on The Basis of AI: Margaon Bridge Junga Bridge local nala
Administrative Approval Detail : एन0एच0 12014/105/2016/यू0आर0/चारधाम/एन0एच0-2job no. NH-94-UR-2016-17-496
TS Amount (lakhs) : 23780.53 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
23780.00
Resanction Cost :
23780.00
Tentative Cost :
23780.00
Exp. Upto Last Fy : 15,207.72
For CFY 2024-2025
Remaining : 8,572.28
Demand : 1,000.00
Allotment : 256.28
Exp in CFY : 256.28
Total Up to Date Exp : 15,464.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 96 %
Up to Date : 97 %
Sanction on :
7 years 3 months ago
28 Mar 2017
Tentative Completion date:
2 months 2 weeks ago
30 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
physical progress 97.42 %
financial progress-95.20 %
-- as on 06-Jun-2024
Physical Peramenters