Work Profile

67W425 :

No Pic Avilable Time series Gantt
बडखोलू-साकणीखेत-रौतेला-काण्डा-बौसाल मोटर मार्ग का नव निर्माण कार्य।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : 2005/।।।(2)/16-37(एम0एल0ए0)2015 टी0सी0 दि0 27.06.2016

TS Amount (lakhs) : 280.68 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

486.04

Resanction Cost :

280.68

Tentative Cost :

280.68

Exp. Upto Last Fy : 273.53

For CFY 2024-2025

Remaining : 7.15

Demand : 7.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 273.53

Work completed

Physical Progress:

At start of FY 2024-2025 : 100 %

Up to Date : 100 %

Sanction on :
8 years 2 weeks ago
27 Jun 2016


Tentative Completion date:
8 months 1 week from now
31 Mar 2025


Actual Completion Date:
Not Yet Reported


Rating : 119

Remark

Bottelneck: no issue


कार्य पूर्ण। दायित्य शेष। -- as on 07-Jul-2022

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 12 7 7.000 0 0.000 0.000
Currently only Bank Gaurantee information is avilable