Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 7 | 7.000 | 0 | 0.000 | 0.000 |
67W425 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2005/।।।(2)/16-37(एम0एल0ए0)2015 टी0सी0 दि0 27.06.2016
TS Amount (lakhs) : 280.68 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
486.04
Resanction Cost :
280.68
Tentative Cost :
280.68
Exp. Upto Last Fy : 273.53
For CFY 2024-2025
Remaining : 7.15
Demand : 7.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 273.53
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
8 years 2 weeks ago
27 Jun 2016
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। -- as on 07-Jul-2022
Physical Peramenters