Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11.7 | 11.7 | 0.000 | 11.7 | 11.700 | 11.700 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
67W743 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली संख्या-48456 दि0 10.08.2023
TS Amount (lakhs) : 160.48 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
160.48
Resanction Cost :
160.48
Tentative Cost :
160.48
Exp. Upto Last Fy : 19.89
For CFY 2024-2025
Remaining : 140.59
Demand : 100.00
Allotment : 62.76
Exp in CFY : 62.76
Total Up to Date Exp : 82.65
Work completed
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 100 %
Sanction on :
11 months 1 week ago
10 Aug 2023
Tentative Completion date:
3 weeks 1 day ago
25 Jun 2024
Actual Completion Date:
3 weeks 1 day ago
25 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्य शेष। 3.00 कि0मी0 31.03.2024 तक पूर्ण कर लिया गया था। -- as on 27-Jun-2024
Physical Peramenters