Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11.7 | 11.7 | 0.000 | 11.7 | 8.700 | 0.000 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
67W743 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली संख्या-48456 दि0 10.08.2023
TS Amount (lakhs) : 160.48 Lacs
Financial Detail
Sanction Cost : 160.48 Lacs
Resanction Cost : 160.48 Lacs
Exp. Upto Last Fy : 19.89 Lacs
For CFY 2024-2025
Remaining : 140.59 Lacs
Demand : 100.00 Lacs
Allotment : 50.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 19.89 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
9 months 1 week ago
10 Aug 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्र्रगति पर। -- as on 14-Dec-2023
Physical Peramenters