Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.125 | 2.125 | 0.000 | 2.125 | 0.000 | 0.000 |
69W309 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-पत्रावली संख्या -36087, लोक निर्माण अनुभाग-2 दि0 10 नवम्बर 2022
TS Amount (lakhs) : 116.35 Lacs
Financial Detail
Sanction Cost : 116.35 Lacs
Resanction Cost : 121.94 Lacs
Exp. Upto Last Fy : 66.57 Lacs
For CFY 2024-2025
Remaining : 55.37 Lacs
Demand : 45.00 Lacs
Allotment : 7.14 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 66.57 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 39 %
Up to Date : 39 %
Sanction on :
1 year 6 months ago
10 Nov 2022
Tentative Completion date:
1 month 2 weeks ago
30 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
टॉप कोट का कार्य पूर्ण। PC कार्य हेतु कार्यवाही गतिमान है। -- as on 06-Mar-2024