Work Profile Report [70W161]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1648/111(2)/13-52(प्रा0आ0)/2012 दि0 04.03.2013
TS Amount (lakhs) : 14.12 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
39.21
Resanction Cost :
39.21
Tentative Cost :
39.21
Exp. Upto Last Fy :
1.90
For CFY 2024-2025
Remaining :
37.31
Demand :
11.90
Allotment :
4.96
Exp in CFY :
4.96
Total Up to Date Exp :
6.86
Construction Started
Sanction on : 11 years 8 months ago
04 Mar 2013
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
20 %
Tentative Completion date on : 2 months 1 week from now
31 Jan 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रथम चरण के कार्य पूर्ण। मुआवजा गठन की कार्यवाही की जा रही है। -- as on 03-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand