Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
70W241 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1331/।।।(2)/19-36(एम0एल0ए0)/ 2017 टी0सी0 दि0 10.03.2019
TS Amount (lakhs) : 296.67 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
296.67
Resanction Cost :
296.67
Tentative Cost :
296.67
Exp. Upto Last Fy : 288.95
For CFY 2024-2025
Remaining : 7.72
Demand : 7.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 288.95
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
10 Mar 2019
Tentative Completion date:
1 month 2 weeks ago
31 May 2024
Actual Completion Date:
2 months 2 days ago
15 May 2024
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्वों का अन्तिमीकरण किया जा रहा है। -- as on 29-Apr-2024
Physical Peramenters