70W283 :
Administrative Approval Detail : शा0 3324/।।।(2)/21 -11 (मु0मं0घो0)/2015 दिनांक 03.09.2021
TS Amount (lakhs) : 112.19 Lacs
Financial Detail
Sanction Cost : 112.19 Lacs
Resanction Cost : 112.19 Lacs
Exp. Upto Last Fy : 98.90 Lacs
For CFY 2024-2025
Remaining : 13.29 Lacs
Demand : 10.00 Lacs
Allotment : 10.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 98.90 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 90 %
Sanction on :
2 years 8 months ago
03 Sep 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पार्ट-2 का कार्य पूर्ण। एस0डी0बी0सी0 का कार्य प्रगति पर। -- as on 28-Mar-2024
Physical Peramenters