Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8.1 | 8.1 | 0.000 | 8.1 | 8.100 | 8.100 |
70W457 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली संख्या-48456, दिनांक 10.08.2023
TS Amount (lakhs) : 201.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
201.41
Resanction Cost :
201.41
Tentative Cost :
201.41
Exp. Upto Last Fy : 49.73
For CFY 2024-2025
Remaining : 151.68
Demand : 151.68
Allotment : 50.00
Exp in CFY : 127.48
Total Up to Date Exp : 177.21
Work completed
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 100 %
Sanction on :
11 months 1 week ago
10 Aug 2023
Tentative Completion date:
1 day 18 hours from now
19 Jul 2024
Actual Completion Date:
4 weeks 1 day ago
18 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का अन्तिमीकरण किया जा रहा है। -- as on 25-Jun-2024
Physical Peramenters