Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 100 | 100 | 0.000 | 100 | 0.000 | 0.000 |
71W1013 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या 45994 दिनांक 12/03/2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
270.20
Resanction Cost :
270.20
Tentative Cost :
270.20
Exp. Upto Last Fy : 0.05
For CFY 2024-2025
Remaining : 270.15
Demand : 270.00
Allotment : 115.00
Exp in CFY : 145.28
Total Up to Date Exp : 145.33
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 70 %
Sanction on :
4 months 5 days ago
12 Mar 2024
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 06-Apr-2024
Physical Peramenters