Length of Road [Km] | 1 | 1 | 1.000 | 0 | 0.000 | 0.000 |
71W741 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5974/।।। (2)/ 21-41 (एम0एल0ए0)/ 2017 दिनांक 09/12/2021
TS Amount (lakhs) : 52.42 Lacs
Financial Detail
Sanction Cost : 52.42 Lacs
Resanction Cost : 52.42 Lacs
Exp. Upto Last Fy : 44.38 Lacs
For CFY 2024-2025
Remaining : 8.04 Lacs
Demand : 8.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 44.38 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 5 months ago
09 Dec 2021
Tentative Completion date:
4 months 2 weeks ago
31 Dec 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्णं। अवशेष देयकों के भुगतान की कार्यवाही की जा रही है। -- as on 07-Nov-2023