Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 0.000 | 8 | 5.000 | 0.000 |
72W258 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 6443/।।।(2)/15-09(मु0मं0घो0)/2015 दि0 11.09.2015
TS Amount (lakhs) : 333.35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
333.35
Resanction Cost :
333.35
Tentative Cost :
333.35
Exp. Upto Last Fy : 281.60
For CFY 2024-2025
Remaining : 51.75
Demand : 51.75
Allotment : 0.00
Exp in CFY : 51.75
Total Up to Date Exp : 333.35
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 70 %
Sanction on :
8 years 10 months ago
01 Sep 2015
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
किमी0 1 से 5 में पी0सी0 का कार्य पूर्ण। शेष 3.00 किमी0 हेतु पनरीक्षित आगणन गठित किया जा रहा है। -- as on 05-Jun-2024
Physical Peramenters