Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 44.1 | 44.1 | 3.800 | 40.3 | 21.000 | 0.000 |
83W10 :
Administrative Approval Detail : RO/UK/Annual Plan/2020-21/Ranikhet/02 Date 30-12-2020
TS Amount (lakhs) : 4819.55 Lacs
Financial Detail
Sanction Cost : 4,819.55 Lacs
Resanction Cost : 4,819.55 Lacs
Exp. Upto Last Fy : 927.16 Lacs
For CFY 2024-2025
Remaining : 3,892.39 Lacs
Demand : 1,100.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 927.16 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
3 years 4 months ago
30 Dec 2020
Tentative Completion date:
5 months 1 week from now
29 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Total BC 3.800 Km. & DBM 30.350 km. Complete. KC Drain 10100 Rmt. 40 No. Box Culvert Complete & 2 No. Causeway Complete The Contract has been terminated by SE Letter No. 2195/61 Yata NH/2022 Date. 20-06-2023 due to slow progress. अवशेष कार्य की पुनः निविदा आमंत्रित की गई, न्यूनतम निविदादाता मै0 वुडहिल कन्स्ट्रक्शन के नाम अनुबन्ध गठित। कार्य प्रारम्भ। -- as on 04-Apr-2024
Physical Peramenters