Work Profile Report [83W9]
Fin Plan
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : RO/UK/12014/104/Annual Plan/2019-20 Date 31-03-2020
TS Amount (lakhs) : 387.24 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
387.24
Resanction Cost :
387.24
Tentative Cost :
387.24
Exp. Upto Last Fy :
266.35
For CFY 2024-2025
Remaining :
120.89
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
266.35
Work completed
Sanction on : 4 years 4 months ago
31 Mar 2020
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 2 years 7 months ago
16 Dec 2021
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work completed. -- as on 03-Apr-2022
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: 15m Span RCC bridge (Mandalsera Section)