Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 3.9 | 1.500 | 2.4 | 0.000 | 0.000 |
9W15 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2555/।।।(2)/ 06-41(प्रा0आ0)/ 06 दिं0 26.09.2006
TS Amount (lakhs) : 228.57 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
104.40
Resanction Cost :
228.57
Tentative Cost :
228.57
Exp. Upto Last Fy : 215.40
For CFY 2024-2025
Remaining : 13.17
Demand : 14.66
Allotment : 6.00
Exp in CFY : 5.32
Total Up to Date Exp : 220.72
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
17 years 9 months ago
26 Sep 2006
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
3 months 2 weeks ago
31 Mar 2024
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
मार्ग का निर्माण कार्य पूर्ण। -- as on 03-Jul-2024