Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 3.9 | 3.9 | 0 |
9W15 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2555/।।।(2)/ 06-41(प्रा0आ0)/ 06 दिं0 26.09.2006
TS Amount (lakhs) : 228.57 Lacs
Financial Detail
Sanction Cost : 104.40 Lacs
Resanction Cost : 228.57 Lacs
Exp. Upto Last Fy : 215.40 Lacs
For CFY 2024-2025
Remaining : 13.17 Lacs
Demand : 14.66 Lacs
Allotment : 10.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 215.40 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
17 years 7 months ago
26 Sep 2006
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
3.90 किमी0 लम्बाई में पहाड़ कटान एव पार्ट-।। का कार्य का पूर्ण स्कपर निर्माण कार्य प्रगति पर है। वनभूमि की विधिवत् स्वीकृति प्राप्त। मार्ग का निर्माण कार्य पूर्ण। -- as on 26-Apr-2024
Physical Peramenters