Work Profile Report [9W15]
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : 2555/।।।(2)/ 06-41(प्रा0आ0)/ 06 दिं0 26.09.2006
TS Amount (lakhs) : 228.57 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
104.40
Resanction Cost :
228.57
Tentative Cost :
228.57
Exp. Upto Last Fy :
215.40
For CFY 2024-2025
Remaining :
13.17
Demand :
14.66
Allotment :
6.00
Exp in CFY :
5.63
Total Up to Date Exp :
221.03
In Maintenance After Completion
Sanction on : 18 years 2 months ago
26 Sep 2006
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 3 weeks ago
31 Mar 2024
Actual Completion Date : 8 months 3 weeks ago
31 Mar 2024
Physical Linear Components
Remark
मार्ग का निर्माण कार्य पूर्ण। -- as on 03-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: