Work Profile Report [9W15]

कैंची हरतपा मोटर मार्ग के किमी0 4 से तितोली तक मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Nabard
  • Tenders

  • Aggrements
  • Project Activities

  • alerts
  • Documents

    Samples

Administrative Approval Detail : 2555/।।।(2)/ 06-41(प्रा0आ0)/ 06 दिं0 26.09.2006

TS Amount (lakhs) : 228.57 Lacs

Budget Financial Head : NABARD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

104.40

Resanction Cost :

228.57

Tentative Cost :

228.57

Exp. Upto Last Fy :

215.40

For CFY 2024-2025

Remaining :

13.17

Demand :

14.66

Allotment :

6.00

Exp in CFY :

5.63

Total Up to Date Exp :

221.03

In Maintenance After Completion

Sanction on : 18 years 2 months ago

26 Sep 2006

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 8 months 3 weeks ago

31 Mar 2024

Actual Completion Date : 8 months 3 weeks ago

31 Mar 2024

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
6
3.9
1.500
2.4
0.000
0.000

Remark

view all

मार्ग का निर्माण कार्य पूर्ण। -- as on 03-Jul-2024

Rating : 100

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: