Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
9W346 :
Administrative Approval Detail : शा0सं0 1692/।।।(2)/20-58 (एम0एल0ए0)/ 2017 टी0सी0।। दिं0 14.09.2020
TS Amount (lakhs) : 179.08 Lacs
Financial Detail
Sanction Cost : 179.08 Lacs
Resanction Cost : 179.08 Lacs
Exp. Upto Last Fy : 168.32 Lacs
For CFY 2024-2025
Remaining : 10.76 Lacs
Demand : 10.76 Lacs
Allotment : 10.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 168.32 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 8 months ago
14 Sep 2020
Tentative Completion date:
3 months 2 weeks ago
31 Jan 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
2.00 किमी0 लम्बाई मे पी0सी0 , स्कपर आदि का निर्माण कार्य पूर्ण । अतिआवश्यक दीवारो का निर्माण कार्य प्रगति पर है। -- as on 01-Nov-2023
Physical Peramenters