Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.9 | 1.9 | 0.000 | 1.9 | 1.900 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 60 | 60 | 0.000 | 60 | 60.000 | 0.000 |
9W359 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 435/।।।(2)/22-31(प्रा0आ0)2013 दिं0 06.01.2022
TS Amount (lakhs) : 717.09 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
717.09
Resanction Cost :
717.09
Tentative Cost :
717.09
Exp. Upto Last Fy : 517.10
For CFY 2024-2025
Remaining : 199.99
Demand : 199.99
Allotment : 149.00
Exp in CFY : 137.52
Total Up to Date Exp : 654.62
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 80 %
Sanction on :
2 years 6 months ago
06 Jan 2022
Tentative Completion date:
4 weeks 19 hours from now
15 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सेतु के एरेक्शन एवं बियरिगं का कार्य पूर्ण। डेक स्लैब एवं पी0सी0 का कार्य किया जाना है। -- as on 03-Jul-2024
Physical Peramenters