Segment [Id - 12] Detail

NH

235 Km

Road ID: 12

National Highway [NH87E/109]

Jyolikot Almora Karanprayag national highway

ज्योलीकोट अल्मोड़ा कर्णप्रयाग राष्ट्रीय राजमार्ग

Segment ID- 12 :

235.000 Km

Top Surface Condition of A Uniform Segment Section
#/ID Start Chainage End Chainage KM Condition Patches Inventory Date Data status Current Source for Road Surface maintenance
1/12861 0.000 55.500 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56 A: All Ok 0 Jun 04, 2024 Renewel
2/18827 55.500 101.000 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80, 81, 82, 83, 84, 85, 86, 87, 88, 89, 90, 91, 92, 93, 94, 95, 96, 97, 98, 99, 100, 101 B: Moderate Detoriation 0 Mar 12, 2026 DLP
3/18812 101.000 108.600 102, 103, 104, 105, 106, 107, 108, 109 A: All Ok 0 Mar 12, 2026 Renewel
4/18828 108.600 120.000 109, 110, 111, 112, 113, 114, 115, 116, 117, 118, 119, 120 B: Moderate Detoriation 0 Mar 12, 2026 DLP
5/18813 120.000 149.000 121, 122, 123, 124, 125, 126, 127, 128, 129, 130, 131, 132, 133, 134, 135, 136, 137, 138, 139, 140, 141, 142, 143, 144, 145, 146, 147, 148, 149 A: All Ok 0 Mar 12, 2026 DLP
6/18814 149.000 171.000 150, 151, 152, 153, 154, 155, 156, 157, 158, 159, 160, 161, 162, 163, 164, 165, 166, 167, 168, 169, 170, 171 A: All Ok 0 Mar 12, 2026 DLP
7/5857 171.000 200.000 172, 173, 174, 175, 176, 177, 178, 179, 180, 181, 182, 183, 184, 185, 186, 187, 188, 189, 190, 191, 192, 193, 194, 195, 196, 197, 198, 199, 200 A: All Ok 3 Dec 28, 2023 DLP
8/1396 200.000 217.000 201, 202, 203, 204, 205, 206, 207, 208, 209, 210, 211, 212, 213, 214, 215, 216, 217 A: All Ok 0 Nov 20, 2023 AR
9/5858 217.000 234.000 218, 219, 220, 221, 222, 223, 224, 225, 226, 227, 228, 229, 230, 231, 232, 233, 234 A: All Ok 0 Dec 28, 2023 DLP

Patch work history from MIS

For Division Segment ID - 5723 Total Achivement of 18.000 Km Reported by Girish Chandra Pandey, Assistant Engineer Civil, NH Div Ranikhet on 2024-10-15 14:06:11 against Patch Repair 2024-25 (Post-Mansoon)

For Division Segment ID - 8701 Total Achivement of 13.000 Km Reported by Girija Kishore Pandey, Assistant Engineer Civil, NH Div Haldwani on 2025-11-03 11:34:27 against Patch Repair 2025-26 (Post-Mansoon)


Historic Data :

#/ID Chainage Condition Patches Inventory Date Status
1/5273 108.600 - 120.000 A: All Ok 0 Dec 18, 2023 Data treated as old on Mar 12, 2026
2/11718 101.000 - 108.600 D: Renewel Required 3 May 16, 2024 Data treated as old on Mar 12, 2026
3/5283 149.000 - 171.000 A: All Ok 0 Dec 18, 2023 Data treated as old on May 14, 2024
4/5281 120.000 - 149.000 B: Moderate Detoriation 5 Dec 18, 2023 Data treated as old on May 14, 2024
5/5269 101.000 - 108.600 D: Renewel Required 0 Dec 18, 2023 Data treated as old on May 14, 2024
6/5278 89.000 - 101.000 A: All Ok 0 Dec 18, 2023 Data treated as old on May 14, 2024
7/5276 55.550 - 89.000 A: All Ok 0 Dec 18, 2023 Data treated as old on May 14, 2024
8/1399 217.000 - 234.000 A: All Ok 0 Nov 20, 2023 Data treated as old on Dec 28, 2023
9/1389 171.000 - 200.000 A: All Ok 10 Nov 20, 2023 Data treated as old on Dec 28, 2023