6W855 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0-4088/।।।(2)/2023-(पा0आ0)/2023 दिनांक 01.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 60.31 Lacs
Resanction Cost : 60.31 Lacs
Exp. Upto Last Fy : 35.52 Lacs
For CFY 2024-2025
Remaining : 24.79 Lacs
Demand : 24.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 35.52 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 60 %
Sanction on :
6 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
3 months 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
700 मी0 क्रश बैरियर का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 06-Feb-2024